Story

St. Marys Infrastructure Projects Include $4 Million Lift Station, $4 Million Roundabout

November 3, 2026 government, public meetings, infrastructure, st marys, city council
St. Marys Infrastructure Projects Include $4 Million Lift Station, $4 Million Roundabout

City Manager Michael Mahaney provided an extended update on infrastructure projects during his report to the St. Marys City Council on Nov. 2, 2026.

He said a manhole lift station project on Winding Road, near Sugar Mill Elementary, is expected to take about three more weeks and carries a cost he placed at roughly $4 million. The city manager called it a complicated project.

Addressing public confusion about the intersection of Winding Road and Colerain, the city manager said the Georgia Department of Transportation determined the current configuration is necessary for safety reasons due to heavy activity at the intersection. He said a planned roundabout at that location is now estimated to cost $4 million and is described as a 50-50 project shared between Kingsland and St. Marys.

The city manager also reported that representatives from the Georgia Environmental Finance Authority (GEFA) traveled from Atlanta to inspect lift stations numbered 15 and 79. He said the city received a GEFA loan of $3.4 million to fund that work.

Share this story
Printed for Kingsland

Subscribe to the hometown paper

The newspaper

Weekly print edition

The week in Kingsland, on paper. Local stories, events, and where your neighbors stand.

$9.97/mo
Delivered every Sunday · $119.60/yr
Get the newspaper
All Things Camden

Sign In